Today (20 Feb 2025), Mr. Suriya Juangroongruangkit, Deputy Prime Minister and Minister of Transport, revealed the progress of the Pink Line electric train extension project, Sri Rat - Muang Thong Thani section, 2 stations, total distance 3 kilometers (km), investment budget 4,072 million baht, that from data as of the end of January 2025, the overall project progress is 85.97%, divided into civil works 87.88% and systems works 82.22%, 2.17% ahead of schedule.