Full service opening on July 19th, Pink Line MRT enters "Muang Thong Thani"

Today (20 Feb 2025), Mr. Suriya Juangroongruangkit, Deputy Prime Minister and Minister of Transport, revealed the progress of the Pink Line electric train extension project, Sri Rat - Muang Thong Thani section, 2 stations, total distance 3 kilometers (km), investment budget 4,072 million baht, that from data as of the end of January 2025, the overall project progress is 85.97%, divided into civil works 87.88% and systems works 82.22%, 2.17% ahead of schedule.